The floor pour
First they drive little posts in the ground and level them with a string.
The string is then removed and the reinforcement
mat is installed and tied together.
After that little berms are made the height of the little wooden posts.
Then finally one by one the wheelbarrow loads of cement are leveled
off to the height of the berms until the entire floor is completed.
Sunday, May 24, 2009
Plumbing & Stucco
next week.
Saturday, May 16, 2009
Rain,Rain,Rain
Rumor has it it rained 12 inches in 18 hours on Tuesday,
which washed out a little of the access road to the development,
nevertheless the work on the house progressed rather nicely,
electrical boxes were cut in, cuts made in the walls, trenches dug
and holes were made thru the walls
for the plumbing I will be starting to install on Monday.
Much thanks being due to the crew for fixing the road so quickly!
and holes were made thru the walls
Sunday, May 10, 2009
Crown is Completed & Finish Begins
As the framing was being removed from the South side,
the rebar was being tied for the North Crown.
Then the same framing that came off the South side was reinsialled on the North side,
and the Front of the house.
The framing was then poured full of concrete,
and by the end of the week the coating was being applied to the walls!
Saturday, May 2, 2009
Crown,Floor & Septic All Begin