Sunday, July 12, 2009

Away on Vacation!

Well I've been in America for the past month so not a lot of progress.
Did manage to get the slab poured over the well, walls soon!
While I was away the support posts were sanded &
treated and some of the framing wood was delivered.
These next pictures are of my next door neighbors
houses, also in various stages of completion.

Sunday, May 31, 2009

The floor pour

First they drive little posts in the ground and level them with a string.
The string is then removed and the reinforcement
mat is installed and tied together.
After that little berms are made the height of the little wooden posts.
Then finally one by one the wheelbarrow loads of cement are leveled
off to the height of the berms until the entire floor is completed.

Sunday, May 24, 2009

Plumbing & Stucco

This week was focused on covering the brickwork
with stucco for a nice square finish on the walls.
Plus we installed all the plumbing in the floors
to make ready for the pouring of the slab

next week.Both baths & the Kitchen were convienently located on one side of thehouse for ease in plumbing. Here it all is on the completed back wall.

Saturday, May 16, 2009

Rain,Rain,Rain

Rumor has it it rained 12 inches in 18 hours on Tuesday,
which washed out a little of the access road to the development,
nevertheless the work on the house progressed rather nicely,
electrical boxes were cut in, cuts made in the walls, trenches dug
and holes were made thru the walls
for the plumbing I will be starting to install on Monday.
Much thanks being due to the crew for fixing the road so quickly!

Sunday, May 10, 2009

Crown is Completed & Finish Begins

As the framing was being removed from the South side,
the rebar was being tied for the North Crown.Then the same framing that came off the South side was reinsialled on the North side,
and the Front of the house.
The framing was then poured full of concrete,
and by the end of the week the coating was being applied to the walls!

Saturday, May 2, 2009

Crown,Floor & Septic All Begin

It was a pretty exciting week in allthe framing for the crown was done on the South East side
The Floor was then leveled

a little more material addedand then digging the hole for the septic system began
Dont tell OSHA we didn't have our steel-toe boots or safety hats!

Sunday, April 26, 2009

Even more Bricks

This week we finished the North West corner!
Here's the LAST brick being placed!
Soon we will be starting the woodwork. You cant exactly go to "Home Depot" & order up a load of lumber here. Its a little more of a Do-It-Yourself program as you can see in the video below!
AND--- no one got hurt!



Here is a picture of the Rebar that goes inside the "Crown".
Were starting the "Framing" of the Crown on Monday.
Hopefully, well be pouring by Wednesday.

Wednesday, April 8, 2009

Bricks, Bricks, Bricks....

The brickwork has begun.
What has been started will soon be the bathrooms.
Along with the Master Bedroom.The entire south-east corner now complete.
Next week the north-west corner.

Saturday, April 4, 2009

The Pour

We had a mixer delivered,unfortunately our generator
didn't quite have enough guts to power it so we sent it back.

I gotta say, my crew is incredible! They mixed and poured the
entire foundation BY HAND with shovels and wheelbarrows!


And thats the way its done "Rag A Muffin Style"!!
Completed foundation, walls start on Monday.

Friday, March 27, 2009

Ironwork

Homemade jigs for bending and tying the rebar.
Rebar placed in trench and ready to pour concrete.